MS Project Earned Value Calculation

 

I have read this article, it is really cool

http://office.microsoft.com/en-us/project/HA101567921033.aspx

but be aware that the name of the ER terms have been changed in the last PMBOK 3 edition as the following

Old Term

Old abbr.

New Term

New Abbr.

Budgeted cost of work scheduled

BCWS

Planned value

PV

budgeted cost of work performed

BCWP

Earned Value

EV

actual cost of work performed

ACWP

Actual Cost

AC

 

Best regards